Onehunga becomes one of Auckland’s new railway hubs next year but it’s emerged that there are now some important unresolved issues and more funding is needed for the main station development.
Detailed designs are now being prepared for the platform and pedestrian access ways for the new Onehunga station at the former ITM site.
But there are some outstanding funding issues.
A plaza entrance from Onehunga Mall (and pedestrian access from both Princes St and Nielson St) is planned for the station as is a small temporary park and ride but, while these are important components of the overall design, there is no funding for either.
The Railway Enthusiasts Society has also agreed in principle to the relocation of their building, which is the former Onehunga railway station and presently used for the society’s headquarters at 38 Aldred St. But it will cost $282,000 to relocate the heritage station – money also not allocated.
The society’s committee say outstanding issues are the retention of ownership of the building and its heritage style and value; identification and agreement on the occupancy of the building on the land proposed, issues such as rental and security and access by member.
“In terms of timing, relocation would not be favoured prior to the comprehensive development of the site, which property analysts have recommended be considered in the medium term recognising the unfavourable market conditions.”
There is another tricky problem: The designs so far show a significant gradient in the southwest corner to the platform and talks are underway to see whether a gentler gradient can be achieved to ensure ease of access for pedestrians.
Today’s ARC transport committee was told the timing for the Onehunga branch line is no more exact than sometime “by mid-winter next year.”
Other points of interest that emerged:
The Maungakiekie community board also has listed its wants:
And the board’s concerns?
Meanwhile, development work continues.
Workers have rehabilitated the existing single track on its current alignment, renewed rails and sleepers, and upgraded the formation and drainage as necessary. The old track has been removed, earthworks completed and the track replaced at level crossings. Ballasting and tamping of the new track, which currently ends at Galway Road, is underway. Project Dart says its next step is to upgrade eight level crossings along the sign as well as associated pedestrian level crossings.
The junction between the Southern Line at Penrose and the Onehunga branch line will be upgraded to allow remote control of signals and a 30 minute service frequency.
There are managing to stuff this up as Auckland only knows how… Not relocating the bus terminal next door is ridiculous and mainly due to the fact the local Onehunga Business Association is objecting and it’s chairs shop is inbetween the bus terminal and the train station and thinks the people walking between the two will increase his business…
So instead of getting a lot more people in the area and making PT more attractive throughout this area of the city, one guy maybe gets to make a bit more money…
A nice little expose Jon, it’s amazing the amount of work that has had to go into rebuilding this line.